Crews working on Stockton Hill Rd. (Photo courtesy of the City of Kingman)
Kingman

Stockton Hill Road Update

Crews working on Stockton Hill Rd. (Photo courtesy of the City of Kingman)

KINGMAN –Work is continuing on Stockton Hill Road. The City of Kingman has completed the waterline testing and is now awaiting regulatory approval from the state.

Next week, crews will be working on the concrete throughout the project and will begin preparing areas for final tie-ins.

Motorists will encounter small work zones along the roadway. Construction on the culvert is progressing well, and crews have switched traffic control to the other side of Stockton Hill Road.

They will be installing new pipes and concrete structures on the west side next week, as well as patching the trench.